Enppi / Badr Petroleum Company-Shell
Design, Supply, Install, Commissioning and Startup of the ICSS for NEAG-1 field
Dual hot redundant SIEMENS S7400FH, redundant fail safe I/O modules
- Burner Management System (BMS): High availability safety system SIL3,
Dual hot redundant SIEMENS S7400FH), Redundant fail safe I/O modules
- SCADA: 8000 Tag, Redundant server, 50" Monitoring screen
- Industrial Dual Redundant UPS System: 30KVA, NICD batteries,
Back up time 2 HR
- Pressurized Pre-fabricated control module that accommodate the ICSS
- IP 54 Pressurized shelter (18 x 6 x 4.2m L x W x H)
- Raised floor for cabling system
- false ceiling for lighting/fire/HVAC
- Explosion Proof Battery Room
- Fire Alarm and FM200 fire Fighting System for the shelter
Central dual redundant Air conditioning system for the shelter